Batchenga Lena road project

Aspect

  

 
REVIEW PERIOD             JUNE 2019          
PROJECT NAME                                                                      CM-P3 – Batchenga Lena Road Project
FUNDING (LENDER)                          
COST  
PROGRESS REPORT AND EXECUTION RATE /
  • Disbursement rate : 24,24%

    -a global progress report since the last review : 15,55%

    -Reorganisation of Lot 3 and the raising of JICA’s particiaption to 76% to enable the ADB pay SINOGYDROon 4. An amendment is envisaged. T1 was awarded to BALBAKER, T2 to ELEVO et T3 to SINOHYDRO.

    -Construction works are experiencing a clear improvement thanks to the intervention of approved sub contactors

  • Execution rate: 15,55%

DIFFICULTIES/BENEFITS
  • challenges with the reorganisation of the lots,
  • ADB funding will be closed in December 2019 (thre might probably be an extension of the closing date),
  • Slowness in the treatment of amendments,
  • delays in the payment of enterprises and their sub contractors to be improved.
PERSPECTIVES
  • boost works, finalise amendments, booster les travaux, finaliser les avenants, -- -recommend the extension of the closing date for the ADB funding.

 

 

 